SOUTHBRIDGE FIRE STATION

BUILDING PROJECT

ABOUT

The Southbridge Fire Station is more than 125 years old and does not efficiently support the operations of a 21st century fire department. The purpose of this web site is to provide information to the Southbridge community on the facility study process to address the needs of the fire station.

EXISTING 

Trucks and equipment barely fit through the doors, decontamination of trucks and gear is done outdoors, and the building does not meet many local, state and federal codes including ADA accessibility. These are just a few of the inefficiencies of the existing Southbridge Fire Station.

PLANS

Plans and Renderings for a Worcester Street location have been developed and are available for viewing.

PROJECT UPDATE

April 29th, 2025
 

On April 17th, 2025, the Fire Station Building Committee reviewed bids received from five general contractors. The committee voted unanimously to recommend to Town Council to allow the Town Manager to enter into a contract with PDS Engineering & Construction Inc. as the lowest responsible bidder for the construction of the new Southbridge Fire Station.

 

On April 28th, The Town Council voted 7 YES 0 NO to award the Southbridge Fire Station Project to PDS Engineering & Construction Inc. as the responsive and responsible company offering the lowest base bid of $19,940,000.00 plus alternate No. 1 for $60,000.00 for a total contract amount of $20,000,000.00 and allow the Town Manager to sign all related paperwork and contracts.

 

The majority of the funding to complete this project comes from the $25.7 million dollar debt exclusion voted in 2021. In addition, the Town has gained a $1 million-dollar CDS grant through the USDA as well as $913,000.00 through another USDA program. In June of 2024, an additional $1 million dollars was earmarked from free cash for the completion of the project by Town Council. This $1 million will be held as contingency and will only be utilized, if necessary. 

 

The current total budget for the project is $28,613,000.00. To date, $5,025,273.81 has been spent.

 

The Fire Station Building Committee and current project team members look forward to working with PDS Engineering & Construction Inc. moving forward.